Project milestones

Aug 2021 

  • Resource consent granted.
  • Play space and exercise area design starts.
  • Feasibility study for a multi-purpose, community building to replace the pavilion commences.
  • Security fencing in place around active site areas.

Sept 2021 

  • Stormwater and civil works start.
  • Play space design finalised.

Oct to Dec 2021

  • Demolition of existing basketball court and skate park starts.
  • Skate park construction starts.
  • Basketball court and improved vehicle access construction commences.
  • Construction of pathways associated with skate park and basketball court commences.
  • Sports field lighting relocated.
  • Soft opening of skate park.

Jan 2022

  • Shared path construction complete.
  • Main skate bowl and pathways poured.

Feb 2022

  • Basketball court construction complete.
  • Improved vehicle access complete.
  • Play space procurement underway.

March 2022

  • Skate park construction complete.
  • Playground construction commences.
  • RSA memorial wall construction commences.

April 2022

  • RSA memorial wall construction complete.

May to July 2022

  • Playground construction continues.

August 2022

  • New children's playground opens

December 2022

  • Skate park opens to allow skaters to try out the reconstructed ramps and jumps.

January 2023

  • Kia Piki te Ora mural on the skate ramp gets underway.

February 2023

  • New seating, drinking fountains and pathways added.
  • A ‘soft opening’ for the newly completed basketball court and remaining skate park elements, including a new skate bowl and street skate focused area.
  • Shade sails installed over the new playground.
  • New barbeque area with stainless steel barbeque installed.
  • Fitness equipment, including a push-up bar, sit-up bench and leg-lift and parallel bars also installed.
  • Graffiti art works brighten the largest skate bowl.

March 2023

  • Kerikeri Vert Jam stake competition attracts talent from across the country as well as a crowd of spectators.

Last updated: 03 Jul 2024 1:29pm