Kaitāia Water Project
Update
This project is now completed. Information on the Sweetwater Bore and Pipeline built by this project can be found here.
Kaitāia Water Project details
Project type | Water supply infrastructure |
Project value | $15.3 million |
Project status | Completed |
The goal of the Kaitāia Water Project (Sweetwater Bore and Pipeline) was to provide safe, good quality drinking water to the Kaitāia township along with the existing supply from the Awanui River. Now completed, it can supply additional water to boost the water resilience of local households and businesses in Kaitāia. The total project cost was $15.3 million.
The project turned two temporary emergency bores at the Sweetwater site into permanent water sources and also created two new monitoring bores. A 14km pipeline was constructed to transport the water from the Sweetwater bores to Kaitāia’s water treatment plant on Okahu Road.
To find out more about Kaitāia's water supply go here.
The 14km pipeline - view from above
The benefits of the project
Securing a permanent supplementary water source for Kaitāia and improving its drought resilience has been a priority of the council for years and was driven by our Infrastructure and Asset Management Team.
The benefits of this project:
- the ability to provide potable water to the existing Kaitāia water distribution network
- to provide competent legacy workforce for the future of council and Northland infrastructure projects
- to stimulate the Northland economic recovery from the COVID-19 pandemic.
The scope of the project included:
- two production bores to ensure adequate supply and to allow for maintenance
- a pipeline to the water treatment plant at Okahu Road
- and a connection into the water treatment plant.
The bore site includes buffer tanks and a booster pump to convey water from the buffer tanks to the water treatment plant, along with power and telemetry.
Project official opening - June 2022
Project structures
Boresite construction: Works at the bore sites consisted of headworks stainless steel installation for two bores, connecting 390 metres of pipeline, six 25000 litre buffer tanks, a two pump pumpstation with future provision for a third pump, security fencing, a gravel access road and gravel foundations, associated earthworks and reinstatement works.
Main structure: The main structure of the pipeline is the Bonnetts Road pipe bridge. This takes the pipe across the Awanui River. The pipe bridge runs parallel to the current vehicle one-way bridge. It spans 38 metres. The pipe bridge was installed successfully in May 2022 with all connections and air valves constructed. A stainless steel pipe carrier was fabricated and fixed to the existing one-way bridge at Sandhills Road to carry water across the drain.
Transfer pipeline: The 14 km pipeline extends from the bore site, goes through three private properties, follows the road corridor, continues through another private property, then past the college, and along the road reserve until it finally reaches the water treatment plant at Okahu Road in Kaitāia. There are 29 air valves, 13 scour valves and various isolation valves along the pipeline.
Our project update for November
- Over 8700m of pipe has now been installed.
- A maximum of 200m of pipe a day is installed when conditions allow.
- The installation of scour valve and air valve chambers has begun along Bonnetts Rd and on to Gill Rd.
- Pressure testing is ongoing in sections for the pipe that have been installed.
- At the bore sites, platforms have been installed and access roads completed.
Pipe strings on Bird Road.
Scour valve tee and chamber installation on Bonnett Road. Existing emergency water pipelines exposed.
Filling for pressure testing on Gill Road.
Concrete slab at Borehole 2.
Site access track.
Location
Bird Road, Awanui 0486 View Map